2024 Ontario Building Code Changes for Houses and Larger Buildings

The 2024 Ontario Building Code (O. Reg. 163/24) took effect on January 1, 2025, and since April 1, 2025 every building permit application in Ontario must use it. It is based on the 2020 National Building Code of Canada with Ontario amendments.

DDW's drawings and engineering follow the 2024 Code. Below are the changes our clients ask about most, with the Code reference for each.

Secondary Suites: Questions and Answers

What is a secondary suite under the 2024 Ontario Building Code?

A self-contained dwelling unit in a building of only residential occupancy that contains only one other dwelling unit and common spaces, where both units form a single real estate entity. A basement apartment is the most common example. (OBC 1.4.1.2.)

​

What ceiling height does a basement apartment need?

At least 1.95 m in the suite, and 1.85 m clear under beams and ducts. The area that meets these heights must connect to the entrance of each room. (OBC 9.5.3.1.)

​

Do the two units need a fire separation between them?

Walls and floors between the units, and between a unit and shared spaces, can be a continuous smoke-tight barrier of 15.9 mm Type X gypsum board on both sides of walls and on the underside of floor framing. The fire-resistance rating can be waived if the house is sprinklered. Walls, columns and beams that support the floor between the units also need 15.9 mm Type X protection. (OBC 9.10.9.16., 9.10.8.3.)

​

Can the two units share one furnace and duct system?

The furnace and water heater can sit in a shared service room whose walls and ceiling facing either unit or a common space are lined with 15.9 mm Type X gypsum board as a continuous smoke-tight barrier (OBC 9.10.10.4.). The air is a different matter: air from one unit must not be circulated to the other (OBC 6.3.2.7. and 9.33.6.13.(7.1)), and the 2012 Code exception that let a house with two units share return air with a duct smoke detector was removed. In new construction, each unit therefore needs its own air system, for example a separate furnace for each unit, one boiler or combination heating unit feeding a separate air handler in each unit, or ductless heat pumps, with separate ventilation for each unit. When an existing house is converted, Part 11 compliance alternative C201 can allow the existing forced-air system to serve both units if each unit has smoke alarms and a smoke detector in the supply or return duct shuts off the fuel and electrical power to the furnace. We confirm which route fits your house before design starts.

​

What smoke and carbon monoxide alarms are required?

Smoke alarms in both units must be interconnected, by wire or wirelessly, so that one alarm sounds them all. Each shared exit and common area needs its own smoke alarm. Carbon monoxide alarms must also be interconnected across both units and the common spaces. (OBC 9.10.19.3., 9.10.19.5., 9.32.3.9C.)

​

Does a basement suite need a second exit?

Units in a house with a secondary suite are exempt from the rules that require two exit directions or a second exit from a shared corridor. An upper unit needs a second exit only if its door opens onto an exterior passageway more than 1.5 m above the ground that is served by a single stair and has a floor rated under 45 minutes. Bedroom egress window rules still apply. (OBC 9.9.9.2., 9.9.9.3., 9.9.10.)

​

What changed for stairs and doors inside a secondary suite?

Clear height over stairs must be at least 1.95 m, or 1.85 m under beams and ducts in the suite. Doorways in the suite can be sized for 1,890 mm high doors where the lower ceiling height applies. Open risers and handrails that start at a newel post are permitted, and stairs with 4 or more risers need 3-way light switches at the top and bottom. (OBC 9.8.2.2., 9.5.5.1., 9.8.4.9., 9.8.7.2., 9.34.2.3.)

​

How should heating and ventilation be set up?

Keep each unit's air system separate (see the furnace question above). Where each unit has its own heating system, each needs a programmable thermostat located in that unit; where one heating system such as a boiler serves both units, at least one programmable thermostat is required in the house. Shared service rooms, exits and common spaces must be heated to at least 18°C. Shared exits, corridors and ancillary spaces do not need heating-season ventilation, but spaces with exhaust fans need make-up air. (OBC 12.3.1.3., 9.33.3.1., 9.32.1.2.)

​

Are there rules for windows near an inside corner of the house?

Yes. Where exterior walls meet at an angle of 135° or less, unprotected openings into different units must be at least 1.2 m apart. If the units are separated by smoke-tight barriers rather than fire separations, the inside of the exterior wall within that 1.2 m is finished with 15.9 mm Type X gypsum board. (OBC 9.10.12.3.)

​

Is barrier-free design required?

No. The barrier-free requirements of Section 3.8 do not apply to a house with a secondary suite. (OBC 9.5.2.1.)

​

Does zoning allow a secondary suite on my property?

The Building Code sets the construction rules; the municipal zoning by-law decides whether a suite is allowed. Toronto's zoning by-law allows one in a detached house, a semi-detached house or a townhouse. We check the zoning for your address before design starts.

​

Planning a basement apartment or second unit? Email info@ddwbuildingdesign.com with the address and a few photos, and we will tell you what the project needs.

 

What Changed for Houses and Small Buildings (Part 9)

Window fall protection: Openable windows in residential buildings need a guard or a tool-release opening limiter (100 mm maximum opening), unless the bottom of the opening is more than 900 mm above the floor or less than 1.8 m above the ground outside. (OBC 9.8.8.1.)

Radon: New homes need a rough-in for a radon extraction system, unless the space below the floor is designed for a future subfloor depressurization system. (OBC 9.13.4.2., 9.13.4.3.)

Wind and earthquake bracing: A new subsection sets braced wall requirements for wood-frame buildings based on local seismic and wind data, and anchorage now depends on the seismic region. (OBC 9.23.13., 9.23.6.1.)

ICF foundations: Minimum concrete thickness for ICF foundation walls is now 150 mm. (OBC 9.15.4.2.)

Framing spacing: Span tables now use metric spacing of 300, 400 and 600 mm instead of 305, 406 and 610 mm. (OBC Tables 9.23.4.2.)

Ventilation and heating: Mechanical ventilation and heating requirements for houses were substantially rewritten. (OBC 9.32., 9.33.)

 

What Changed for Commercial and Larger Buildings (Part 3)

Fire alarm: A fire alarm system is now required in every sprinklered building, with narrow exceptions for NFPA 13D home systems and very small systems. (OBC 3.2.4.1.)

Sprinklers: If a storey must be sprinklered, every storey below it must be sprinklered too. More building classifications now require sprinklers. (OBC 3.2.2.18.)

Egress in unsprinklered floors: Smaller room areas and shorter travel distances. For example, residential suites drop from 150 m² to 100 m², and the distance to the egress door from 25 m to 15 m. (OBC 3.3.1.5.)

Exit doors: Minimum exit doorway width for most occupancies is now 850 mm. (OBC 3.4.3.2.)

Power door operators: Retail and industrial buildings are no longer exempt. Self-closing doors on the barrier-free route from the entrance to suites off a public corridor also need power operators. (OBC 3.8.3.3.)

 

Which building code applies to my permit in Ontario?

The 2024 Ontario Building Code. From April 1, 2025, all permit applications must use it. Projects that applied under the 2012 Code during the transition period keep that Code only if construction starts within six months of the permit being issued.

Email info@ddwbuildingdesign.com to check how the 2024 Code affects your project.

Disclaimer: This page is a plain-language summary for general information only. It is not legal, engineering, architectural or other professional advice, and it does not replace the Ontario Building Code (O. Reg. 163/24), municipal by-laws, or the decisions of the chief building official. Requirements depend on the specific building, its use and its existing conditions, and they can change. Always confirm the current requirements for your project with the full Code, your municipality and a qualified professional before you design, build or renovate. Reading this page does not create a client relationship with DDW Building Design and Consulting Ltd., and DDW accepts no liability for any loss or damage arising from reliance on this information without a project-specific review. Last reviewed: November 2026.

info@ddwbuildingdesign.com

Serving the GTA (Toronto, Mississauga, Brampton, Vaughan, Markham, Oakville), Hamilton, Kitchener-Waterloo, Guelph, London, Aylmer and Peterborough

Authorized by the Association of Professional Engineers of Ontario to offer professional engineering services.

Architectural services provided under a Certificate of Practice issued by the Ontario Association of Architects.

Our team includes a Certified Engineering Technologist (C.E.T.), certified by OACETT.

Professional Engineers Ontario logo. DDW holds a PEO Certificate of Authorization
Ontario Association of Architects logo. DDW holds an OAA Certificate of Practice
Contact Us
Project Type

© 2026 DDW Building Design and Consulting Ltd. Information on this website is general and is not professional advice. Confirm requirements for your project with a qualified professional and your municipality.

bottom of page